Wind Turbine Component PROPOSED Delivery Schedule | ||||
5th April 2021 to 18th April 2021 | ||||
DAY | DATE | DELIVERIES | ||
Monday | 5th April | 0 – Public Holiday | ||
Tuesday | 6th April | 0 | ||
Wednesday | 7th April | 3 | ||
Thursday | 8th April | 4 | ||
Friday | 9th April | 5 | ||
Saturday | 10th April | 0 | ||
Monday | 12th April | 3 | ||
Tuesday | 13th April | 4 | ||
Wednesday | 14th April | 5 | ||
Thursday | 15th April | 3 | ||
Friday | 16th April | 4 | ||
Saturday | 17th April | 5 | ||
Police escorted deliveries to the Bango Wind Farm generally occur earlier than 7:00am as permitted in accordance with Condition L4.2b of EPL 21286, and Condition 6 of Schedule 3 of SSD 6686. | ||||
Note that the scheduled transporting of the Wind Turbine Components can and do change due to unplanned reasons – including inclement weather conditions. These schedules are completely at the management of RMS NSW and the NSW Police. |